Local citizens who rely on Highway 12 were told not to worry when they brought up their concerns to Exxon representatives at last summers open house. They were assured by the Kearl Oil Project spokesmen that Mammoet was the best shipper in the business. When asked about the specifics of the road and how these megaloads would handle things like rock faces, ice, landslides, soft shoulders, etc. the representatives seemed unfamiliar with the nature of Highway 12 and unable to give adequate answers. Instead of taking the concerns of local citizens seriously Exxon spent time and money on a PR campaign to make it look like this project would benefit the local economy while ignoring the many ways this transportation project could hurt the area.
Now, almost a year later, on the first night of the Exxon's Test Validation Module there were problems. The Exxon megaload hit a guy wire that knocked the power out to 1,300 homes and shut the highway down for over an hour.
ITD has asked the shipper, Mammoet, to address the problems from last night before they continue their journey. I would like to ask ITD to consider this transportation plan from the point of view of local residents who rely on Highway 12. Knocking out power and shutting down the highway are minor issues compared with what could happen with these loads. But even these types of minor problems could result in a life or death delay for someone racing to the hospital.
We've learned over the past year that there are other routes available to these megaload modules. We've learned they can be broken down into smaller units and shipped on alternate routes. We've also learned that these megaloads can be made on site in Alberta. So why does ITD and Exxon continue to push for an unsafe use of Highway 12?
Here's more info on Exxon's trouble Monday night:
Big rig test module hits wire, cuts power to 1,300 homes, businesses off Highway 12 by Kim Briggeman, Missoulian, 4/12/11
The big blue megaload that a Canadian oil company says will validate its plan to send many more up U.S. Highway 12 in Idaho and Montana got off to a rough start.
The 30-foot-high load hit a guy wire near Orofino, Idaho, early Tuesday, setting off a sequence of events that led to power outages in some 1,300 area homes and businesses for almost five hours, and causing the highway to be closed for an hour.
It happened around 1:45 a.m., a few hours after the big rig struck and broke off a giant tree branch near the Lewiston Rose Garden as it left town. The branch was 10 inches in diameter and 20 feet long. No traffic delays resulted.
Imperial Oil/ExxonMobil's practice load finished the night parked 13 miles short of its designated stopover near Kooskia. It appeared the plan to make the 182-mile trip to Lolo Hot Springs in Montana by Thursday morning was off....ITD ... said Mammoet would not be allowed to proceed with the move until [an investigative] report had been received and approved.
"When we're working with haulers and shippers, our approach is to have an exchange of information with them and to improve transportation plans moving forward," Rush said. "We don't like to levy fines right from the get-go or flat out deny people permits, but we do ask them to make changes.".... Read more:
http://missoulian.com/news/local/article_4ba1f8a4-654c-11e0-82d1-001cc4c002e0.html
Showing posts with label test module. Show all posts
Showing posts with label test module. Show all posts
Wednesday, April 13, 2011
Tuesday, April 5, 2011
Exxon Test Module Postponed Once Again - Locals Recommend Megaloads Stay Off Fragile Highway 12

The first mention in the press of an Exxon megaload test module came in the fall of 2009. The test run was postponed until the spring of 2010, early summer, late summer and eventually fall of 2010. At the start of 2011 Exxon and ITD started putting out specific dates – February 22nd, February 28th, March 7th, March 28th and most recently April 4th. The reasons have varied over the course of the past year and half as to why the test module hasn’t been run. Yet the fact remains – Highway 12 is ill-suited to to be a megaload transportation route.
If you still think these loads have a future on Highway 12, I recommend you drive the route today. Look at the signs of rockfall and landslides – both large and small along the route. Notice the extra large potholes that have surfaced since the two Conoco loads labored over the route. Then look to the side and check out the river. With steady ran for the past week on top of better than average snowfall the creeks are all flowing at top capacity feeding the Lochsa and Clearwater Rivers into a frenzy. These are not the conditions to “test” out loads 200 tons over the national weight limit standard setfor interstate highways. Even with the weight distributed over numerous axels the pressure on the highway bed is much greater than that of a normal semi-truck. What effect will those weights have on the roadbed? How will pullouts that were not built to handle loads anywhere near this size hold up in these conditions? How does driving such a load at slow speeds with the increased noise and vibration affect all ready unstable hillsides? And what happens if there’s any kind of major problem?
These questions and many others were raised by local citizens at the informational meetings held in Kooskia last summer. Residents were told that Mammoet was the “best in the business” and that Highway 12 was the only route these modules could take. Since then we’ve learned that Mammoet had two accidents on dry, wide roads in the past year and that many of the modules can be broken down into smaller shipments as is evidenced by the work currently taking place at the Port of Lewiston. The representatives for Exxon/Imperial showed a general lack of knowledge relating to the nature of Highway 12 – they seemed unaware of snow and ice that covers the upriver section of the road for much of the winter as well as the risk of avalanche, the spring run-off and the landslides and rockslides that often accompany it as well as the large volume of summer traffic.
The best business decision Exxon can make at this point is to pack up those loads, ship them back down the Columbia and take the traditional route – through the Gulf of Mexico and up the central U.S. Had Conoco done that when they first ran into trouble their shipments would have arrived in Billings long ago.